The following ODOT construction projects are anticipated to affect highways in Adams County. All outlined work is weather permitting. Visit OHGO.com for travel updates or follow the Ohio Department of Transportation (ODOT) District 9 on Facebook or Twitter for current Adams County construction information.


State Route 781

S.R. 781 Slide RepairA slide repair project on S.R. 781 between Mineral Springs Road and Jones Road. This project will begin on October 27.

Continuing Impacts: S.R. 781 will be closed from 7 a.m. — 3:30 p.m. for the duration of the project; Traffic will be detoured via S.R. 348 to S.R. 125 to S.R. 41.

Estimated completion: October 31

State Route 136

S.R. 136 Tree TrimmingA tree trimming project on S.R. 136 between McGlothen Road and Old Cincinnati Pike. This project will begin on October 20.

Continuing Impacts: S.R. 136 will be closed from 7 a.m. — 3:30 p.m. for the duration of the project; Traffic will be detoured via S.R. 125 to S.R. 41.

Estimated completion: October 24

State Route 247

S.R. 247 ResurfacingA resurfacing project on S.R. 247 between S.R. 125 and U.S. 52. This project has begun as of September 8.

Continuing Impacts: S.R. 247 will be closed for the duration of the project; Traffic will be detoured via S.R. 41 to S.R. 136 to U.S. 52.

Estimated completion: Fall 2025

State Route 348

S.R. 348 ResurfacingA resurfacing project on S.R. 348 between the Scioto County line and S.R. 125. This project has begun as of August 5.

Continuing Impats: S.R. 348 will experience daily closures in sections; raffic will be detoured via S.R. 781 to S.R. 41 to S.R. 125.

Estimated completion: Fall 2025